A Cook County, Illinois, Circuit Court judge has temporarily halted odor-causing operations at Pullman Innovations’ plant on Chicago’s Southeast Side following a lawsuit alleging excessive odors and violations of environmental laws.
Illinois Attorney General Kwame Raoul and the city of Chicago requested the temporary restraining order against A-F Acquisition LLC, which operates as Pullman Innovations. The order remains in effect until Jan. 14, 2027, when the next hearing is scheduled, or until the facility addresses the excessive odors and complies with environmental laws before that date.
The facility converts a by-product of commercial edible oil production into animal feed ingredients. In August, Raoul, Chicago Mayor Brandon Johnson and the city filed a lawsuit alleging that the company caused excessive odors and illegal air pollution, constructed a boiler without a permit that could cause or contribute to air pollution, and violated conditions of its operating permit.
The lawsuit follows complaints from residents who reported that the odors forced them to keep their windows closed, disrupted outdoor activities and interrupted family events. Nearby schools and a local church have also been affected, with churchgoers reporting that odors interfered with weddings, funerals and outdoor festivals.
Chicago inspectors encountered odors during multiple inspections in response to complaints, with some reporting difficulty breathing and nausea. Illinois Environmental Protection Agency inspectors observed extremely strong odors inside and outside the facility during a February 2025 inspection. In August 2026, an agency inspector again encountered overpowering odors in residential areas near the plant.
Community members have supported the state's case by tracking and documenting odors, providing affidavits and keeping the attorney general's office and the Illinois Environmental Protection Agency informed about conditions at the facility.
A hearing is scheduled for Jan. 14 on a motion by Raoul and the city seeking a preliminary injunction that would require Pullman Innovations to address the odors and violations of environmental laws and its operating permit.
The motion includes a proposed timeline for the company to submit a remediation plan to the Illinois Environmental Protection Agency for approval and implement the plan once approved. It also seeks an order requiring the company to complete installation and begin operating a regenerative thermal oxidizer, a pollution control device, within 120 days. Additional requirements would address identifying and controlling odors to prevent future violations.
Source: Office of the Illinois Attorney General, "ATTORNEY GENERAL RAOUL SUCCESSFULLY HALTS PULLMAN PLANT OPERATIONS OVER EXCESSIVE ODORS AND ENVIRONMENTAL LAW VIOLATIONS"